Kelmscott Park Construction Update – October 2018

The Condominiums at Kelmscott Park Speed Towards Completion

The Focus construction teams finish exterior work and begin to focus on the finer interior details as we head into the final months of construction onsite.

The previous month

October was an exciting time onsite at Kelmscott Park. Teams began tackling the last aspects of exterior work on the condo building including the iconic stone entries and large stone patios and balconies. A new amenity patio and fire pit also took shape at the north end of the building.

However, the majority of work this month took place indoors. Teams finalized installation of the cabinets in kitchens and bathrooms on the first floor, drywall on the second and spray foam insulation in the ceilings on the third floor.

The single-family homes at Kelmscott Park made progress in October as well. Our second and third homes are now both completely framed out. We also had our first home closing, and we welcomed the first official residents of Kelmscott Park!

In the coming month

During November, our team will continue to focus on the interior of the building. Our schedule anticipates that we will start installing cabinetry on the second floor and drywall installation will begin on the 3rd floor following homeowner walk throughs.

The exterior of the building will start to look polished towards the end of the month. We anticipate having most of the patio and balcony work done and will begin work on the landscaping surrounding the building.

Single family home construction continues to progress.  With one home now closed, 2 others are wrapping up exterior façade construction and another is currently wrapping up the design phase.