Kelmscott Park Construction Update – May 2018

May marked a busy time on site at Kelmscott Park as teams frame the first condominium building and install perennial and smaller plants around the finished apartment buildings.

 A crane is on site to enable teams to place the large, prefabricated steel framing system for the first condominium building at Kelmscott Park. The building system enables teams to move quickly and since beginning the framing work at the end of April, crews are now placing the gables of the roof. The speed of this building method means that teams are projecting to complete the exterior framing by the end of June and will have begun interior wall framing as well.

The Kelmscott Apartments continue to increase in occupancy as teams install the greens and gardens that will help to define the project. Along Western Ave in the North East corner of the community, one of the Kelmscott Pocket Parks has been completed and teams are working on a second park in the Southeast corner where the Kelmscott Park Sales Center use to sit.